If you already have solar panels, adding battery storage does not automatically mean replacing the solar inverter you already own. In many existing systems, an AC-coupled battery can be added on the AC side while the existing solar installation continues to operate.
That does not make AC coupling the right answer for every home. The sensible route depends first on the inverter and architecture already installed, then on factors such as FIT or SEG metering, the Distribution Network Operator (DNO) connection route, phase arrangement, battery-control metering and any backup requirement. This guide helps you decide what should stay, what may need changing and what to verify before choosing the battery.
In short
In many existing solar installations, you can add battery storage without replacing the current PV inverter. Start by identifying whether your inverter is a healthy solar-only inverter, an existing hybrid inverter with a documented battery route, or equipment that is already due for replacement. That decision determines whether an AC-coupled retrofit or a wider hybrid/DC redesign is the more useful option to compare.
Can you add a battery without replacing your solar inverter?
Often, yes. An AC-coupled battery has its own power-conversion and control arrangement and connects on the AC side of the home energy system. That can allow the existing solar panels and PV inverter to continue doing the job they already do.
The alternative is to redesign more of the system around a compatible hybrid or DC-coupled architecture. That can become relevant when the current inverter already supports a documented battery route, when the inverter needs replacing anyway, or when a larger PV redesign is already planned.
Neither architecture is automatically better. Keeping the existing inverter can reduce the amount of the current PV system that needs changing, while replacing or reconfiguring it may make sense when there is already a technical reason to redesign the system. Compatibility, metering, DNO requirements and the functions you want still need to be checked in either case.
The first question is not which battery to buy. It is whether your existing inverter should remain part of the system.

Start with the inverter you already have
Before comparing battery models, identify the manufacturer, exact model and type of inverter already installed. That gives you three useful starting situations.
Your existing solar-only inverter is healthy
If the inverter is working correctly and there is no wider reason to replace the PV system, compare an AC-coupled retrofit first. The existing solar inverter can potentially remain in service while a separate battery system is added on the AC side.
This still requires a system-level check. AC coupling does not prove that every battery, meter, phase arrangement or control configuration will work with the installation.
You already have a compatible hybrid inverter
If your inverter is already a hybrid model, check its manufacturer-approved battery route before adding a separate AC-coupled system. The exact inverter model, firmware, supported batteries, metering arrangement and installation requirements matter; the word hybrid alone is not enough to establish compatibility.
Where a documented battery route already exists, comparing that route with an AC-coupled retrofit gives you a more useful choice than assuming the existing inverter must either stay or be replaced.
Your inverter is ageing, failing or already due for replacement
If inverter replacement is already justified for technical or maintenance reasons, compare the cost and architecture of keeping the existing arrangement temporarily with redesigning the system around a compatible hybrid inverter.
Age by itself should not be turned into a fixed replacement rule. Condition, faults, remaining support, warranty position, the proposed battery and any planned PV expansion are more useful evidence for the decision.
AC-coupled vs hybrid retrofit: what actually changes?
The useful difference is not a universal claim that one architecture is cheaper, easier or more efficient. It is what happens to the system you already own and which compatibility questions the new design creates.
This is why generic AC-vs-DC efficiency percentages or a generic retrofit price difference are not enough to choose the architecture for an existing home. The existing equipment and the changes actually required are more important.
What should you collect from your existing solar system?
A useful installer or manufacturer conversation starts with evidence about the system already installed. Record what you can from existing paperwork, labels and previous DNO or installer documents. You should not open electrical covers or take measurements on live equipment yourself.
Practical checklist
These details do not choose the battery for you. They let the installer or manufacturer check the real architecture instead of answering a vague question such as whether a battery “works with solar”.
What can make an existing-solar retrofit more complicated?
FIT and SEG
Having a legacy Feed-in Tariff does not automatically prevent a battery retrofit, but the metering and payment arrangement should be checked before the installation is altered. Ofgem's FIT generator guidance says battery storage connected to an accredited installation must be notified to the relevant FIT licensee and explains that generation and, where applicable, metered export must remain measurable separately from other sources for the corresponding payments.
For co-located storage, Ofgem's current co-location guidance covers how storage interacts with FIT and SEG arrangements. That matters particularly where the battery can also charge from the grid and the source of exported electricity may affect the payment arrangement.
The Smart Export Guarantee applies to eligible installations in Great Britain, and individual SEG licensees set their own tariff and contract terms. Check the proposed change with the relevant licensee rather than treating “SEG compatible” as a universal battery feature. See Ofgem's SEG guidance for generators.
DNO, G98, G99 and export limits
In Great Britain, battery storage has to be considered as part of the network connection assessment. The route is based on the complete generating-and-storage arrangement, including the relevant per-phase capacity and configuration. Battery capacity in kWh is not the figure that decides whether G98 or G99 applies. The Energy Networks Association's energy-storage connection information places storage within the G98/G99 connection framework.
If you want the detailed homeowner decision route, see our guide to G98 and G99 for home battery storage.
An export limitation scheme may also form part of the design. ENA Engineering Recommendation G100 covers customer export and import limitation schemes, but using an export limit does not make the wider connection assessment disappear. See the current ENA G100 publication.
Note: These G98/G99 statements describe the Great Britain framework. Northern Ireland uses separate network-connection arrangements, so the Great Britain route should not be applied there unchanged.
Battery-control metering is not the same as payment metering
Several different devices may all be described casually as a “meter”, but they do different jobs. A battery energy meter or current transformer (CT) can provide live import, export or load data to the battery control system. A FIT generation meter, export/payment meter and supplier smart meter exist for different measurement, scheme or settlement purposes.
Do not assume that the meter or CT used to control the battery replaces a FIT meter, export meter or supplier meter. If this is the part of the retrofit you need to resolve, see our guide to home battery meters and CT clamps.
Microinverters, three-phase systems and unusual architectures
Microinverters, multiple PV inverters, unusual legacy metering or a three-phase supply do not automatically rule out a retrofit. They do make the architecture more important to confirm. The installer needs to know where solar generation is converted to AC, which phases the existing and proposed equipment use, what the control meter can observe and how the complete installation is presented to the network.
That is why a brand-by-brand compatibility list would be misleading here. Compatibility has to be established for the exact models and proposed configuration rather than inferred from the fact that a battery is AC-coupled.
Backup during a power cut
Adding battery storage does not by itself mean the home will continue operating during a grid outage. Backup depends on the exact product capability, switching arrangement, circuits connected to the backup supply, available power and energy, and the design of the electrical installation.
If backup matters to you, define that requirement before choosing the battery. Our guide to home battery backup during a power cut explains the difference between a dedicated backup output, selected backed-up circuits and wider whole-home arrangements.
How our S2400 and S2400 AC fit into an existing-solar decision
For an existing solar installation where the current PV inverter is intended to remain, our S2400 AC is the dedicated AC-coupled route to assess. It is designed without direct PV input, so the existing solar system remains a separate part of the home energy architecture.
Our current S2400 AC documentation also describes CT-based measurement of energy flow associated with a third-party inverter. That measurement capability should not be read as a universal compatibility certificate for every inverter. The exact meter or CT arrangement, phase configuration and supported system topology still need to be confirmed for the proposed installation.
Our S2400 provides a different architectural option. It has two direct PV inputs, each supporting up to 1,000 Wp under the current product specification, and it can also be integrated into an existing solar PV system through AC coupling. That can be relevant where new or additional compatible panels may connect directly to the battery system as part of the wider design.
Neither route removes the earlier checks. Start with the existing inverter and architecture, then confirm metering, phases, DNO requirements and the functions you actually need before treating either model as the right configuration for the home.
What should you check next?
Once you know whether the existing inverter should stay, move to the unresolved question rather than trying to solve cost, sizing, metering and backup all at once.
- DNO route: check which G98 or G99 route may apply to the complete installation.
- Battery sizing: compare your typical evening and overnight consumption with the energy regularly available for charging before choosing capacity.
- Installed cost: compare the complete project scope in our UK home battery cost guide.
- Financial case: test household-specific assumptions with our guide to whether a home battery is worth it.
- Meter or CT: identify what needs measuring with our meter and CT guide.
- Power-cut operation: define the intended outage behaviour using our battery backup guide.
- FIT or SEG: confirm the existing payment and metering arrangement before changing how electricity can flow through the installation.
The aim is to arrive at the battery decision with the architecture already understood. That makes product comparison much more useful than choosing a battery first and discovering the integration constraints afterwards.